Once the overall funding
available is known, the project budget should be set. This should
include all likely costs including:
Cost of demolition, building and site works;
Furniture and fittings;
Professional fees, if appropriate.
The pie chart opposite
shows a typical percentage breakdown for a school project. The professional
consultant should develop a detailed cost plan, which should be
maintained and kept under review throughout the project. Once the
contract figure is agreed, the client should avoid asking for changes
to design or the specification, as even small changes can substantially
add to the cost of the project owing to the delay and disruption
they can cause to the contractor. Although the cost plan should
include a contingency sum for unforeseen circumstances, this is
not intended to cover changes in the brief or the design.
3.6 BUILDING
PROCUREMENT
There are various ways
of undertaking building works at schools, but the four main methods
are:
'Traditional' procurement;
Design and Build;
Public Private Partnerships;
Partnering.
These are described below.
A summary of the main pros and cons of each is shown in the table
right.
'Traditional'
procurement
Traditional procurement
is still the most common form of procurement for small and medium
size projects. The client, either the LEA or school, will normally
commission consultants to prepare designs and specifications for
works that are then constructed by a contractor engaged separately.
The contractor is likely to engage sub-contractors for actual construction
on site. Traditionally, the contractor offering the lowest bid for
the work would be awarded the contract. Once the building contract
is finished, the consultants and contractor have limited long-term
responsibility for the subsequent performance of the building. Disadvantages
of this method include: difficulty in utilising at the most appropriate
time the full range of skills and experience of those involved;
a focus on initial rather than lifetime costs; a potentially adversarial
contractual relationship with greater risk of cost and time overruns.
|
Design and Build
There are many variants on design and build contracts and in many
instances initial design work will be undertaken by the client before
transfer to the
design and build contractor.
Thereafter the contractor takes single-point responsibility for
the design and construction. The contractor usually employs consultants
for the design element and sub-contractors for the actual construction
work. This form of procurement has particular application to fairly
simple or standardised buildings, for example, sports halls.
It may be possible for the Design and Build option to be extended
to cover maintenance and operation of the facility. This offers
the opportunity for adopting innovative solutions that provide greater
value for money when considering lifetime costs.
Public Private
Partnerships
PPPs are increasingly becoming the main form of procurement for
large projects in the schools sector. With PPP, one contractor provides
and operates the assets over an extended period, usually 25-30 years.
PPP is still a relatively new form of procurement and its application
is developing rapidly. PPP at present typically involves the client
specifying outputs as opposed to inputs. The benefits of PPP solutions
include: greater risk transfer to the private sector partner; use
of private sector management to reduce costs; more innovative solutions
that offer the possibility of higher quality provision, wider social
benefits from more ambitious schemes, and commercial utilisation
that can cross-subsidise the project.
PPP procurement is more complex than traditional methods and therefore
is less well suited to small building contracts under about £10
million in value. However, a number of smaller projects within a
single LEA can be rolled into a single contract to make this method
more feasible.
|
|